Application of commissioning to a VAV system renovation project

Xia Chunhai, Han Zheng, Zhu Yingxin, Xu Guohai

2015.02.02

With an example of VAV system renovation project, presents the steps of commissioning for existing buildings in detail and the relationship of the owner, consultant, control company and design organization in commissioning processes. On the basis of testing data, analyses the energy consumption level of the project and emphasizes the significance of further commissioning. Concludes the systematic method for the commissioning of existing buildings.